| Priority | Subject | Due Date | Status | Progress | Category | Actions | |
|---|---|---|---|---|---|---|---|
| High | Prepare Exchange 2016/2019 Cutover ChecklistVerify mailbox mapping, retention dumpster policies, and shared calendar sync. | Sep 17, 2026 | In Progress |
60% |
Engineering | ||
| Normal | Deploy Disposable Container Test ClusterTier 2 ephemeral verification suite. | Sep 18, 2026 | In Progress |
40% |
Engineering | ||
| Normal | Review Gromox 3.10 SQLite Schema & Migration ToolingCheck dbop version compatibility and pure C# zcore mapping. | Sep 20, 2026 | Not Started |
0% |
Review | ||
| High | Verify DKIM & SPF Public DNS RecordsValidated 2048-bit RSA keys via dig and Admin console. | Sep 14, 2026 | Completed |
100% |
Release |